- Construction Site Chronicle
- |
- 15 February 2023
Winter is coming to an end and the weather was not harsh for our teams building the second stage of the GROEN Housing Estate.
We are pleased to present a list of completed works and those still in progress:
We have completed:
- all foundation works,
- load-bearing walls of the ground floor,
- all ceilings above the ground floor,
- the floor on the ground.
We are currently proceeding with:
- ceilings above the first floor,
- walls of the first floor and attics,
- works related to external installations,
- roadworks,
- works related to the roof truss.
We would like to remind you that you can also find current information concerning the life of Groen Konstancin on Facebook and Instagram.